What has actually been installed, published and delivered — as distinct from what the project was designed to achieve.
Position as at 31 December 2025.
| Installation | Sector | Collector area | Commissioned |
|---|---|---|---|
| NDDB dairy projects (13 installations) | Dairy processing | 7,809 m² | 2018 |
| CEMCOT tannery CETP, Chennai | Leather effluent treatment | 1,590 m² | — |
| Silk reeling unit, Dehradun | Silk reeling | 295 m² | 2017 |
| Natural Capsules Ltd, Puducherry | Pharmaceuticals | 282 m² | 2021 |
| Total commissioned | 9,976 m² | 38% of target |
A further seven lighthouse projects — six MSME units and Goa Medical College — are under implementation, adding approximately 5,000 m². The Goa Medical College project received approval for 50% financial incentive in January 2026, with the Goa Energy Development Agency as implementing partner.
A four-day Training of Trainers programme was delivered at Goa in June 2024, rated between 4.65 and 4.97 out of 5.0 by participants. Thirty-five operators were trained at ni-msme, Hyderabad in June 2025. Five state dissemination workshops and more than fourteen business meets have been held. A national programme of 20 cluster awareness workshops and 12 technical training programmes runs across four zones through 2026.
Three suppliers have been empanelled following a transparent process against five published criteria covering turnover, years of solar experience, completed projects, qualified professionals and demonstrated technical competence. Enterprises may procure from an empanelled supplier on a single-source basis, or from any other supplier against a minimum of three competitive quotations.